REPLACING SELECTOR ROD JOINT
Remove exhaust assembly 18 00 020.
1980 Models:
Detach heat shield.


Siehe auch 18 00 020
63326014 - click to zoom
 
Unscrew guard.
Installation: Tightening torque¹).


Siehe auch ¹) See Specifications
63326015 - click to zoom
 
To prevent stress in Giubo coupling and therefore
vibration and drumming, use Special Tool
26 1 011 for removal and installation of propeller
shaft.
Unscrew bolts.
Installation: Use stop nuts only once.

73023027 - click to zoom
 
Tighten Special Tool 26 1 011 until bolts can
be removed by hand.

73023028 - click to zoom
 
Installation: To prevent stress in Giubo coupling
only tighten nuts (never bolts).
Tightening torque¹).
Tighten nuts before removing special tool.


Siehe auch ¹) See Specifications
63326016 - click to zoom
 
Remove heat shield.

63026027 - click to zoom
 
Detach center bearing.
Installation: Preload center bearing forward by
distance (A) = about 2 mm (0.080´´).

63026013 - click to zoom
 
Bend down propeller shaft and pull out of centering
pin on transmission.
Important: Don´t disconnect propeller shaft
at slide.

63026014 - click to zoom
 
Installation: Check center, lubricating with
Longterm 2 if necessary.
Replace a damaged center.

63026016 - click to zoom
 
Engage reverse gear.
Remove circlip (1).
Take off washer (2).
Pull out selector rod (3).

73025011 - click to zoom
 
Push back locking sleeve (1).
Move selector shaft to 3rd gear position.
Knock out pin upward far enough that selector
rod joint can be pulled off of shaft.

63025019 - click to zoom
 
Lubricate joint and bearing bushing with
Longterm 2.@@:

63025020 - click to zoom
 
Vehicles after change point in 1982
REPLACING SHIFT ROD
JOINT
Transmission 260:
Unscrew propeller shaft on transmission - see 26 11 000.
Engage fifth gear.
Lift out circlip (1).
Remove washer (2).
Pull out shift rod (3).
Note:
Transmission 260:
Insert shift rod from the left side as seen looking forward in car.
Transmission 265:
Insert from the right side.


Siehe auch 26 11 000
73025050 - click to zoom
 
Push back the locking sleeve.

2025008 - click to zoom
 
Drive out pin.
Pull out shift rod with joint.

2025009 - click to zoom
 
Installation:
Lubricate bearing sleeve and shift rod joint with Molykote Longterm 2.
Note:
Transmission 260:
Bearing sleeve is offset to the right.
Transmission 265:
Bearing sleeve is offset to the left.

2025010 - click to zoom